h1. Wells Monitoring (Manual and Automatic  Piezometer)
2 1 Giulio Di Anastasio
3 1 Giulio Di Anastasio
h2. Manual- Using tape with a sensor
4 1 Giulio Di Anastasio
5 1 Giulio Di Anastasio
Timings: The person assigned the job of monitoring collects the readings in three slots.
6 1 Giulio Di Anastasio
7 1 Giulio Di Anastasio
1.	Between 6 am to 7 am till about 9 am to 10 am.
8 1 Giulio Di Anastasio
2.	Between 11 am and 1 pm
9 1 Giulio Di Anastasio
3.	Between 2 pm and 5 pm
10 1 Giulio Di Anastasio
11 1 Giulio Di Anastasio
Things required:
12 1 Giulio Di Anastasio
•	Notebook
13 1 Giulio Di Anastasio
•	Pen
14 1 Giulio Di Anastasio
•	Measuring tape
15 1 Giulio Di Anastasio
•	Vehicle for movement
16 1 Giulio Di Anastasio
17 1 Giulio Di Anastasio
18 1 Giulio Di Anastasio
*Ethics*- 
19 1 Giulio Di Anastasio
•	The monitoring should happen in coordination with the community members/ care taker (assigned by the person in charge from within the community). There should be a clear communication from monitor side as to which days the monitoring of a well has to happen and at around what time so that it can be made sure that the pump is not turned on before monitoring. In case a pump was turned on in a well, the monitor should have a gap of about 5 hours on the same day before going again for monitoring.
20 1 Giulio Di Anastasio
•	The monitor should have contact numbers of the person in charge/ care taker for any communication.
21 1 Giulio Di Anastasio
•	If the monitoring is stopped for any reason at any point, the monitor should communicate the same to the person concerned.
22 1 Giulio Di Anastasio
•	The monitor shall take responsibility to inform any kind of changes in a well in terms of its functioning etc.
23 1 Giulio Di Anastasio
•	The monitor should report to the CSR Geomatics Team who has responsibility to publish data.
24 1 Giulio Di Anastasio
•	The monitor published the data to the website and works with the geomatics team.
25 1 Giulio Di Anastasio
26 1 Giulio Di Anastasio
27 1 Giulio Di Anastasio
*Definitions*:
28 1 Giulio Di Anastasio
A master file is maintained with the records of the wells from the field. It is updated when a new well is located. The following set of information are filled out in the Masterfile. 
29 1 Giulio Di Anastasio
30 1 Giulio Di Anastasio
*Well type*
31 1 Giulio Di Anastasio
1.	Open
32 1 Giulio Di Anastasio
2.	Borewell
33 1 Giulio Di Anastasio
3.	Dug cum borewell
34 1 Giulio Di Anastasio
35 1 Giulio Di Anastasio
*Well status*
36 1 Giulio Di Anastasio
1.	In use
37 1 Giulio Di Anastasio
2.	Not in use
38 1 Giulio Di Anastasio
3.	Closed
39 1 Giulio Di Anastasio
40 1 Giulio Di Anastasio
*Pump Status*
41 1 Giulio Di Anastasio
1.	Functioning
42 1 Giulio Di Anastasio
2.	Not functioning
43 1 Giulio Di Anastasio
44 1 Giulio Di Anastasio
*Pump Automation*
45 1 Giulio Di Anastasio
1.	Manual 
46 1 Giulio Di Anastasio
2.	Automatic
47 1 Giulio Di Anastasio
48 1 Giulio Di Anastasio
* Non-accessibility factors*
49 1 Giulio Di Anastasio
1.	Dogs
50 1 Giulio Di Anastasio
2.	Heavy slab
51 1 Giulio Di Anastasio
3.	Narrow casing
52 1 Giulio Di Anastasio
4.	enclosed/locked
53 1 Giulio Di Anastasio
5.	permission
54 1 Giulio Di Anastasio
55 1 Giulio Di Anastasio
*Data Matching Accuracy (reconnecting with harvest wells data)*
56 1 Giulio Di Anastasio
1.	High
57 1 Giulio Di Anastasio
2.	Medium
58 1 Giulio Di Anastasio
3.	Low
59 1 Giulio Di Anastasio
60 1 Giulio Di Anastasio
*Well coordinates*
61 1 Giulio Di Anastasio
For a new well, coordinates of the well position are taken on a mobile GPS.
62 1 Giulio Di Anastasio
Person In charge
63 1 Giulio Di Anastasio
For communication purpose, contact the person in charge as recorded in directory.
64 1 Giulio Di Anastasio
65 1 Giulio Di Anastasio
h2. Automatic- Piezometer (by bala, to be edited) 
66 1 Giulio Di Anastasio
67 1 Giulio Di Anastasio
The calibrations and setting are already done by Azha
68 1 Giulio Di Anastasio
The piezometer is taken to the site of unused well. First the depth and Water level  is checked manually using water meter
69 1 Giulio Di Anastasio
Then the sensor of the piezometer is inserted into the well 1m above the bottom of the well, so the sensor does not get affected from mud or water inside
70 1 Giulio Di Anastasio
The sensor sends the data to an electronic board which translates the signal into the proper output, and then it sends the signal to the transmitting device above, on the ground surface. The transmitter then sends it to the receiver at CSR, the signal is then routed to Talam office through Interneet, enters the software and the reading is processed.
71 1 Giulio Di Anastasio
The piezometer sometimes does not have proper signal and so it would not be able to send it